The project’s formal Chinese name is 阳江市综合文化中心, rendered here as Yangjiang Comprehensive Cultural Center.
The earlier English label “Yangjiang Seven Museums” is not a correct formal name. “七馆合一” was the construction shorthand for seven independently operated civic and cultural venues brought together in one complex; the seven are not all museums. This case preserves the four photographs published in December 2024 while separating official project facts, architect credits and LOPO’s dated product record.

Name, location and seven-venue programme
The Guangdong local-chronicles record places the project in Chengnan New Area, Yangjiang, Guangdong, and says it was renamed Yangjiang Comprehensive Cultural Center in 2022. The architect-submitted project profile gives the more specific address as 250 Siwei Avenue, Jiangcheng District, on the north side of Moyang Lake Park.
The seven institutions are the Yangjiang City Archives, Party History Museum, Local Chronicles Museum, Hall of Fame, Museum, Planning Exhibition Hall and Municipal Workers’ Cultural Palace. The Yangjiang discipline-inspection authority’s 2022 construction record confirms the same composition. “Seven venues in one” therefore describes programme integration, not a complex of seven museums.
Design, construction and opening record
| Client / delivery oversight | The architect-submitted project data names Yangjiang City Agent Construction Project Management Bureau as client. A 2024 local report says the bureau coordinated the project’s construction. |
|---|---|
| Architects | Project data supplied by the architects credits Architectural Design & Research Institute of SCUT Co., Ltd. and Yifang Design Group Co., Ltd.; lead architects are Qiu Jianfa and Bao Ying. |
| Specialist design | The same project record credits Dongsan Interior Design Studio for interior design and Yazhong Curtain Wall Technology Co., Ltd. for curtain-wall design. |
| Construction team | No reliable checked source names the general contractor, facade contractor, terracotta installer or supervision company. These roles remain unresolved rather than being inferred from photographs. |
| Construction / completion | The official record says construction began at the end of 2020 and the centre was completed and put into use in 2024. The architect profile separately gives September 2023 as its completion year; this is treated as a building-project milestone, not proof that all seven venues opened then. |
| Publication date | The WordPress article was published on 3 December 2024 GMT. That editorial date is not used as the completion or opening date. |

LOPO product and role: what the records establish
The architect-submitted project data lists LOPO as the material brand. A 2024 Nanfang Plus project report says the Architectural Design & Research Institute of SCUT and LOPO Art Ceramics jointly developed the project-specific composite ceramic-rod facade. This supports a project-material and design-development relationship, but not an expanded claim that LOPO designed or installed the complete curtain wall.
LOPO’s supplier archive identifies the product as a white-glazed, rectangular terracotta baguette, item TCY400120003, with published axes W400 × H120 × L900 mm. Its related product page describes the item as customized for this project and says the cross-section changed during design development from 150 × 400 mm to 120 × 400 mm. Those are dated supplier fields, not a current standard-SKU promise or a transferable specification.

Keep site, building, exhibition and facade quantities separate
| Official municipal history | 19,569 m² total land area and approximately 37,393 m² total building area. This is the preferred public-project record, but neither figure is facade area. |
|---|---|
| Architect-submitted profile | 8,645 m² land area and 35,634 m² gross built area. The source does not explain the difference from the official figures, so these values stay attributed and are not reconciled by assumption. |
| LOPO’s 2023 supplier story | 22,150 m² site area and 37,515 m² overall floor area. These supplier-side development figures conflict with the later official record and do not describe LOPO’s supply quantity. |
| Two exhibition fit-outs | The official review separately records a 530 m² Local Chronicles exhibition hall and a 623 m² Hall of Fame exhibition hall still under fit-out when its record was prepared. They are not total exhibition area, total building area or facade area. |
| Terracotta facade | Not publicly quantified in the checked sources. No safe square-metre or unit total can be derived from the building areas or photographs. |
For contractual reuse, obtain the owner’s final as-built area schedule and the facade bill of quantities. Do not average conflicting records, sum the two fit-out areas into a whole-project exhibition figure, or convert gross floor area into a ceramic-screen quantity.
Facade intent is not measured performance
The architects describe a parameter-controlled vertical ceramic-rod screen whose angle and height vary around the curved elevations. They present it as a sunshade strategy and part of the building’s wave-like composition. That is a documented design intent. The checked public pages do not provide the calculation files, approved system drawings, project test reports or post-occupancy data needed to publish a quantified energy, thermal, daylight or comfort result.
The photographs can show repetition, curvature, spacing, angle changes and interfaces with glazing and the white metal support layer. They cannot establish fire behaviour, structural or wind capacity, falling-object resistance, water management, glaze durability, corrosion protection, cleaning access, maintenance interval, environmental impact or service life.

Evidence needed before using this facade as a precedent
- the owner-approved project identity, final milestone record, appointment matrix and general/facade contracts;
- the approved baguette code, full axes, section, wall thickness, chambers, tolerances, glaze sample and batch range;
- elevation quantities by type, angle and length, with purchase, delivery and installed-status records;
- rails, keels, anchors, movement, drainage, corners, terminations, openings and access/replacement routes;
- project-specific structural, wind, seismic, falling-object, fire, weathering and glaze evidence; and
- mock-up approvals, installation inspections, cleaning method, replacement stock and as-built handover.
Use the historical item only as a project reference. Review the current Terracotta Baguette category and request current project-specific samples, drawings, reports, availability and commercial terms rather than assuming that TCY400120003 remains a standard offering.
Review a project-specific terracotta louver facade
Share the project location, elevations, required profile and glaze, quantities by type, support concept, exposure, performance criteria, mock-up plan, programme and evidence schedule. For an exact Yangjiang reference, include the approved TCY400120003 drawing and original project records.