This is a facade handover and stage-evidence guide—not a second Anglicare Woolooware Shores case study. The separate Woolooware Shores Stage 6 case owns the project team, 2018–2020 package and LOPO’s dated baguette supply record. This page uses the later archive media to coordinate inspection, resident-facing interfaces, maintenance and change control without duplicating those facts.
The building use makes clear handover records especially important, but a senior-living or aged-care label does not prove accessibility, safety, comfort, shading, ventilation, energy, durability or resident outcomes. Those depend on the complete project design, verified construction and continuing operation.
Keep the Stage 6 case and the handover guide separate
| Record | What it owns | What it must not imply |
|---|---|---|
| Post 9209: Stage 6 case | Anglicare as client, Growthbuilt as design-and-construction builder, Jackson Teece Architects, Woolooware Shores NSW, November 2018–July 2020, Stage 6 scope and the supplier archive’s product fields. | Later-stage product use, whole-masterplan quantities, system performance or current product availability. |
| Post 10131: this guide | Stage/photo attribution checks plus an aged-care facade inspection, interface, cleaning, replacement and asset-handover register. | A duplicate case, three-stage LOPO supply claim, resident outcome, performance proof or a new contract-role statement. |
| Current project records | Official project/stage identity, team, programme and built scope; controlled project records must establish exact facade zones and as-built fields. | That every visible vertical element is terracotta, one product applies across stages or the supplier authored the design/system. |
Growthbuilt’s official Stage 6 page records 42 independent-living units, 48 residential aged-care places and community areas, with Anglicare as client and Jackson Teece Architects as architect. Jackson Teece’s broader project page describes 183 senior-living apartments and 48 care places across six new buildings. Keep the Stage 6 package and wider development total distinct.
Treat later archive views as evidence leads, not phase proof

Use a photo register with attachment ID, original file, photographer/rights, capture date, building/stage, elevation/zone, depicted component and evidence source. A view can guide inspection only after it has been tied to an as-built elevation; visual similarity is not a stage or product match.
Archive product fields: LOPO’s 2021 Stage 6 record states white terracotta baguettes, nominal 50 × 100 mm, and a cumulative quantity of 6,000 linear metres. That is neither 6,000 m² nor 6,000 pieces. The 2024 follow-up separately claimed individual lengths of 510–1600 mm without a controlling source. Do not combine or reuse these fields without the Stage 6 submittal, order, cutting schedule and packing record.
Coordinate the resident-facing facade interfaces
A vertical screen beside balconies, walkways or shared spaces has visual and physical interfaces that must be resolved by the project team. The material image does not establish the screen’s function or compliance.
Reach and contact
Map reachable low-level elements, projections, sharp edges, pinch/entrapment zones, impact exposure and any climbability concern under the applicable brief and rules.
Guards and falls
Identify the code-compliant guard separately from the decorative or shading screen. Verify openings, loads, fixings, deflection and failure containment for the complete assembly.
Views and privacy
Record the intended sightline, privacy and daylight balance from occupied positions. A repeated vertical rhythm does not guarantee any outcome.
Paths and entries
Check clear width, headroom, door/wayfinding visibility, mobility-device movement, maintenance access and temporary exclusion zones.
Water and fire
Coordinate facade drainage, interfaces, cavity/fire strategy, adjacent membranes and non-combustible requirements for the actual wall and screen arrangement.
Cleaning and replacement
Define safe access, cleaning method, acceptable chemicals/tools, breakage isolation, lifting/removal route, spare storage and resident communication.

Build an as-built screen and baguette register
| Register field | Required record | Handover use |
|---|---|---|
| Zone identity | Building/stage, elevation, level, grid, balcony/path/entry interface and marked as-built location. | Prevents a detail, photo or spare from being applied to the wrong stage or zone. |
| Component | Exact product/custom drawing, section, cut length, finish/batch, orientation, quantity and approved appearance range. | Supports accurate inspection, replacement and matching without photo-derived assumptions. |
| Support and safety | As-built rails/brackets/connectors/anchors/substrate, reinforcement/restraint, loads, movement, tolerances, guard relationship and temporary states. | Links the visible element to the engineered load path and safe maintenance method. |
| Enclosure and fire | Joints, adjacent cladding, drainage, membranes/insulation, cavity/fire barriers, openings, compatibility and approved deviations. | Keeps the screen from being treated as the complete weather, thermal or fire system. |
| Quality record | Samples/mock-up, inspections/hold points, test references, damage/repairs, NCRs, substitutions and close-out disposition. | Shows what was accepted, changed or repaired—and by whom and when. |
| Operations | Cleaning/inspection method and interval set by responsible parties, access equipment, isolation plan, spares, warranty/contact, replacement sequence and record owner. | Makes maintenance repeatable without turning this article into a universal method. |
Each field needs a document number, revision, date, responsible party and acceptance status. If the record does not identify the exact stage and zone, it is not ready for operations or for use as a precedent on another project.
Keep factory imagery separate from project acceptance

For a project match, require a traceable item/drawing and finish, purchase/order reference, stage/zone quantity, packing list, batch/inspection record and receipt-to-installation chain. A handwritten mark or similar colour/profile in a photograph is not enough.
See the current Terracotta Baguette page as a product-family starting point, then confirm current manufacture, exact dimensions/finish, support assumptions, evidence and availability for the new project.
Reopen the review for every later stage or change
Identify
Name building, official stage, elevation/zone and controlling package; do not use informal “North/South/West” labels without source mapping.
Compare
List what changed from the precedent: geometry, product, spacing, supports, substrate, guard, enclosure/fire interface, exposure and access.
Recalculate
Have responsible engineers review loads, deflection, connections, fracture/fall risk, movement and temporary/permanent conditions.
Requalify
Match samples, mock-up/tests and approvals to the exact new configuration; prior-stage photographs or acceptance are not transferable.
Release
State whether the exact revision is released for sample, procurement, manufacture, installation or operations, with conditions and approvers.
Hand over
Update as-builts, asset register, inspections/NCRs, cleaning/access, spares, warranty and replacement records for the completed zone.
Do not turn building use or appearance into performance
- energy saving, heat-gain reduction, natural ventilation, indoor-air quality, privacy or acoustic comfort;
- corrosion, weathering, colour retention, durability, impact resistance, low maintenance or waterfront suitability;
- fire, structural, guard, water, accessibility or code performance of the complete assembly;
- reduced carbon, sustainability, environmental preference or green-building achievement;
- resident health, safety, wellbeing, independence, social connection or quality-of-life outcomes; or
- LOPO design, engineering, installation, testing, whole-system or multi-stage supply responsibility.
These matters require exact products and assemblies, current project conditions, applicable standards and approvals, defined methods/boundaries, responsible-party review and dated records. The archive images are visual references only.
Prepare a stage-specific facade handover pack
Share the official stage/zone plan, as-built elevations/details, exact product and batch schedule, supports/guards/interfaces, approval and NCR register, image/source manifest, inspection and access strategy, cleaning/replacement requirements, spares/warranty and responsible contacts. Keep the 2021 Stage 6 case as the project reference and use this guide to close the operations record.